Agra Metro

Summary

Agra Metro is a rapid transit network in Agra, the fourth largest city in the Indian state of Uttar Pradesh. The Detailed Project Report (DPR) was submitted in 2014 and cleared by the Uttar Pradesh cabinet in 2015. However, due to the formation of a new government and a new Metro Rail Policy, a revised feasibility report was created with the government finally approving it on the 6 March 2024. The Agra Metro is set to consist of two metro lines, with a total length of 29.65 kilometres (18.42 mi).

Agra Metro
UPMRC logo
UPMRC logo
Overview
OwnerUttar Pradesh Metro Rail Corporation
Area servedAgra
LocaleAgra, Uttar Pradesh
Transit typeRapid transit
Number of lines2
Line number
  • Yellow Line
  • Blue Line
Number of stations27 (Phase 1)
6 (priority corridor)
Websitewww.lmrcl.com
Operation
Began operationMarch 6, 2024; 22 days ago (2024-03-06)
CharacterElevated & Underground
Train length3 Coaches
Technical
System length29.65 km (Phase-1)
5.2 km (priority corridor)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail
Average speed34.0 km/h (21.1 mph)[1][2]
Top speed90 km/h (56 mph)
System map

Represents Agra metro route with updated station name.

Once completed it will be the 2nd fastest urban transit system in Uttar Pradesh after Meerut Metro and Delhi Meerut RRTS.

Agra Metro & Taj Mahal

History edit

As of July 2016, DPR has been prepared by RITES and submitted to the state government.[3]

On 28 February 2019, Union Cabinet approved the metro project in Agra worth 8379.62 crore.[4][5]

6 March 2024: Prime Minister Narendra Modi inaugurated the first stretch of Agra Metro Project.

Project highlights edit

The cost of construction is estimated at 350 crore per km. The cost will be evaluated based on the June 2015 price index.

Agra Metro Rail Project will have 2 corridors that will pass through the heart of the city and will connect prominent tourist places including Taj Mahal, Agra Fort, and Sikandra as well as ISBT, Raja Ki Mandi railway station, Medical College, Agra Cantonment railway station, Collectorate, Sanjay Place, and surrounding densely populated residential areas.

Highlights of these corridors include:

  1. The length of Sikandra to Taj East Gate corridor 14.00 km, which is partly elevated and partly underground and comprises 13 stations (6-Elevated and 7-Underground).
  2. The length of Agra Cantt to Kalindi Vihar corridor is 15.40 km comprising 14 stations all elevated.
  3. The estimated cost of the project is 8,379.62 crore and the project will be completed in five years.

About 20 lakh population of the city is expected to be benefitted by Agra Metro Rail Project directly and indirectly at the time of commencement of commercial operations.

The proposed corridors will be having Multimodal Integration with Railway Stations & BRTS Stations and will have a feeder network of Bus, Intermediate Public Transport (IPT), and Non-Motorized Transport (NMT). The Project will have non-fare box revenue from rental & advertisement as well as Value Capture Financing (VCF) through the mechanism of Transit-Oriented Development (TOD) and Transfer of Development Rights (TDR).

The Agra Metro became operational on 6 March 2024.[6]

Route network edit

Phase 1 edit

In Phase 1, 14 metro stations will be built on the Yellow Line (Line 1) from Sikandra to Taj East Gate and 15 metro stations will be built on the Blue Line (Line 2) from Agra Cantt to Kalindi Vihar.[7]

Line Name Terminals Length Stations
Yellow Line Sikandara Taj East Gate 14.27 km 14
Blue Line Agra Cantt Kalindi Vihar 15.40 km 15
Total 29.67 km 29

Current Phases edit

Phase 1
Line Name Terminals Length Stations Opening Date
Yellow Line Sikandra Mankameshwar Mandir 9.07 km 8 Under construction
Mankameshwar Taj East Gate 6 km[8] 6 6 March 2024
Blue Line Agra Cantt Kalindi Vihar 15.40 km 16 Planned
Total 29.67 km 29

Current network edit

Agra Metro
Line Name First Operational Last Extension Station Length Terminal Rolling Stock Track Gauge Electrification
Yellow Line 6 March 2024 N/A 6 5.2 km Mankameshwar Mandir Taj East Gate Alstom MOVIA 1,435 mm (4 ft 8+12 in) 750 V DC third rail

Rolling stock edit

In 2020, Bombardier Transportation won the contract to supply the rolling stock and the signalling system, and the project received conditional clearance from the Supreme Court.[9][10]However the contract was cancelled and Alstom was chosen to supply the rolling stock for the Yellow line. The rolling stock resembles those that run on the Kanpur Metro. On 6 March 2023, the first set of coaches arrived at the Taj Station of the Yellow line from Alstom's manufacturing facility at Savli in Gujarat.

Status updates edit

  • July 2016: Detailed Project Report submitted to the State Government.[11]
  • September 2017: The central government rejected the DPR of Agra Metro as it didn't conform with the new Metro Rail Policy 2017 introduced that month.[12]
  • January 2018: The UP Government Cabinet decides to build metros in Meerut, Kanpur, and Agra.[13]
  • September 2018: Detailed Project Report (DPR) sent by the UP Government to the Central Government.[14]
  • 7 February 2019: The UP Government has allocated 175 crore to start preliminary work in budget.[15]
  • 28 February 2019: Central Government approved the metro project in Agra.[16]
  • 8 March 2019: Foundation stone laid down by Prime Minister Narendra Modi.[17]
  • August 2019: LMRC has requested relevant authorities to transfer land for Metro construction.[18]
  • January 2020: Construction work yet to start as few permissions from the Supreme Court of India, Taj Trapezium Zone Authority (TTZ), Forest department, Archaeological Survey of India and others other departments are pending. Once permissions are in place, land acquisition will take another 3 months.[19]
  • 15 June 2020: TYPSA - Italferr JV wins General Consultant contract[20]
  • July 2020: Bombardier Transportation won the Agra Metro and Kanpur Metro rolling stock and signalling contract. Agra Metro project gets conditional clearance from the Supreme Court. The project which was stuck due to the court stay will now progress fast.[9][10]
  • October 2020: Contract awarded for construction for three metro stations.[21] Civil engineering work to start in December 2020.[22]
  • December 2020: Prime Minister Narendra Modi inaugurated the construction work at the Agra Metro Project Site on 7 December 2020.[23]
  • April 2021: In Agra metro priority section, a total of 688 piles are to be constructed in the 3 km long portion on Fatehabad Road, in which 344 piles are ready, 10 pillars are built, and digging is continued for 3 metro stations.
  • May 2021: UP Metro has built 400 piles out of a total of 686 in the priority section of the Agra Metro project. With this, 45 pile-caps and 16 pillars are also ready. The work of a zero discharge facility at Agra Metro depot is also at a rapid pace. For the zero discharge facility, several underground tanks of different capacities will be built in the Agra Metro Depot complex. For zero discharge facility, a joint water treatment plant of 1 lakh litre capacity will be set up at Agra Metro Depot. In this water treatment plant, the grey water coming out from the kitchen, washroom, floor cleaning, will be recycled. For this, a plant with a capacity of 70,000 litres will be installed. Similarly, a 30,000 litres capacity plant will be set up to treat such black water by washing the coach and whatever other chemical-rich water will come out. Both the plants will be built in the same building so that they can be used in a better way.[citation needed]
  • June 2021: Construction of depot line for Agra Metro has begun with the commencement of piling work on the depot line with 13 piles already constructed so far.} The depot line will connect the mainline with the Metro Depot which is under construction at PAC Ground where metro trains will be stabled and maintained. For the depot line, a total of 500 piles, 39 pile capes, and 34 piers will be constructed.[citation needed]
  • June 2021: The casting of the concourse beam of Taj East Gate, the first metro station of Agra Metro, has also started. The piling work has already been completed with the construction of 69 piles of Taj East Gate Metro Station. Currently, the pillars are being constructed in the side grid of Taj East Gate Metro Station. Soon the construction of the concourse level will also start.[citation needed]
  • June 2021: Along with the construction of the Agra Metro Project Priority Section (Taj East Gate to Jama Masjid), UP Metro has also started the construction of the Depot Line. For this, along with starting the piling, the construction of 13 piles has also been completed. The covered train stabling yard, integrated workshop, and pit wheel length are being constructed in Agra Metro Depot with the new PEB (Pre Engineering Building) technique.[citation needed]
  • July 2021: European Investment Bank (EIB) to fund 480 mn euros for Agra Metro Rail Project.[24]
  • August 2021: Unique codes of all metro stations in Agra Metro Rail Project get approved by Indian Railways, as of 7 August.[25]
  • August 2021: European Investment Bank (EIB) approves and is ready to fund 480 mn euros for Agra Metro Rail Project, as of 10 August.[26]
  • Aug 2021: Taj East Gate Metro Station takes shape, and it will be the first metro station of Agra Metro to be completed, as of 24 August.[27]
  • September 2021: Construction begins of Agra Metro's second metro station, Basai Metro Station.[28]
  • October 2021: Tenders invited for electrification contract for Agra Metro.[29]
  • December 2021: Work on Agra Metro's third metro station, Fatehabad Metro Station, is expected to be completed by December-end.[30]
  • July 2023 : Trial run begins.[31]
  • March 2024: Prime Minister Narendra Modi inaugurated the priority corridor section of Agra Metro on 6 March 2024.[32]

See also edit

References edit

  1. ^ "Agra Metro - Information, Route Map, Fares, Tenders & Updates". The Metro Rail Guy. Retrieved 6 March 2024.
  2. ^ "Agra Metro: Information, Route Maps & Project Updates". Metro Rail News. 8 August 2023. Retrieved 6 March 2024.
  3. ^ "मेट्रो का सपना कहीं सपना ही न रह जाए" [Metro project remains pending in Agra]. Agra City News. 16 February 2016. Archived from the original on 3 July 2017. Retrieved 9 October 2017.
  4. ^ "Kanpur & Agra metro projects get cabinet nod". Business Standard India. Press Trust of India. 28 February 2019. Retrieved 28 February 2019.
  5. ^ "Centre approves Agra, Kanpur metro rail projects". aninews.in. Retrieved 28 February 2019.
  6. ^ "PM Modi to flag off Agra Metro priority corridor: Route, price, other details". Mint. 5 March 2024. Retrieved 5 March 2024.
  7. ^ "Agra Metro – Information, Route Maps, Fares, Tenders & Updates". The Metro Rail Guy. Retrieved 19 December 2020.
  8. ^ Rao, Lingamgunta Nirmitha (6 March 2024). "Now, reach Taj Mahal by Metro. PM to launch Agra 'priority corridor' today". Hindustan Times. Retrieved 6 March 2024.
  9. ^ a b "Agra Metro Project: अब आएगी रफ्तार, अगले सप्ताह से शुरू होगा मेट्रो के लिए ये काम". Dainik Jagran (in Hindi). 24 July 2020. Retrieved 16 August 2020.
  10. ^ a b IANS (24 July 2020). "Decks cleared for Agra Metro project, with conditions". www.daijiworld.com. Retrieved 16 August 2020.
  11. ^ "Uttar Pradesh govt gets DPRs for Meerut, Agra". The Indian Express. 1 July 2016. Archived from the original on 6 February 2017. Retrieved 9 October 2017.
  12. ^ "Centre rejects metro rail project report - Times of India". The Times of India. 16 September 2017. Archived from the original on 9 October 2017. Retrieved 9 October 2017.
  13. ^ "UP to Start Metro Services in Agra, Kanpur and Meerut". 18 January 2018.
  14. ^ "UP govt sent DPR to Union govt". 5 September 2018.
  15. ^ Anurag Gupta (8 February 2019). "कानपुर-आगरा को जल्द मिलेगी मेट्रो की सौगात, 350 करोड़ रुपयों से पकड़ेगी रफ्तार". Dainik Jagaran (in Hindi). Retrieved 20 March 2019.
  16. ^ "Adityanath thanks Modi for clearing Agra, Kanpur Metro projects". Outlook. Retrieved 20 March 2019.
  17. ^ "कानपुर से पीएम मोदी ने किया आगरा मेट्रो का शिलान्यास, ताजनगरी में हुआ सीधा प्रसारण". Amar Ujala (in Hindi). 8 March 2019. Retrieved 20 March 2019.
  18. ^ "तेजी सेे बढ़ रही आगरा की मेट्रो, स्टेशनों के लिए जमीन हस्तांतरण की तैयारी Agra News". Dainik Jagran (in Hindi). 22 August 2019. Retrieved 29 August 2019.
  19. ^ "Work on Agra Metro yet to start; may miss deadline | Agra News - Times of India". The Times of India. 21 January 2020. Retrieved 29 January 2020.
  20. ^ "TYPSA-Italferr JV Wins Kanpur & Agra Metro's General Consultancy". The Metro Rail Guy. 15 June 2020. Retrieved 15 June 2020.
  21. ^ Rai, M. K. (23 October 2020). "Agra Metro Line-1's Construction Works Worth Rs 272 Crores Set for award to Sam India". Metro Rail News. Retrieved 30 October 2020.
  22. ^ "दिसंबर से शुरू होगा आगरा मेट्रो का काम, 273 करोड़ की लागत से बनेंगे तीन प्रमुख स्टेशन". Amar Ujala (in Hindi). 21 October 2020. Retrieved 30 October 2020.
  23. ^ "Narendra Modi: PM Narendra Modi inaugurates construction work | Agra News - Times of India". The Times of India. 7 December 2020. Retrieved 7 December 2020.
  24. ^ "EIB to fund Agra metro rail project: UPMRC". Hindustan Times. 29 July 2021. Retrieved 28 September 2021.
  25. ^ "Agra Metro Rail Project: आगरा मेट्रो के सभी स्टेशनों के यूनिक कोड को मिली मंजूरी, अब इन नामों से भी जाने जाएंगे ये स्टेशन". Dainik Jagran (in Hindi). Retrieved 28 September 2021.
  26. ^ "EIB agrees to fund 480 million euros for Agra Metro Rail Project". Urban Transport News. Retrieved 28 September 2021.
  27. ^ "Agra Metro Rail Project: जल्द आकार लेने लगेगा आगरा का ये मेट्रो स्टेशन, रखा गया पहला डबल टी गर्डर". Dainik Jagran (in Hindi). Retrieved 28 September 2021.
  28. ^ "आगरा मेट्रो के काम ने पकड़ी रफ्तार: ताज पूर्वी के साथ अब बसई स्टेशन पर कार्य शुरू, दस महीने में 102 पिलर का निर्माण". Amar Ujala (in Hindi). Retrieved 28 September 2021.
  29. ^ "Tender invited for electrification contract for Agra Metro Rail Project". Urban Transport News. Retrieved 23 October 2021.
  30. ^ "आगरा में मेट्रो: तीसरे स्टेशन का काम दिसंबर अंत में होगा पूरा, निर्माण के दौरान ताजमहल की खूबसूरत तस्वीर आई सामने". Amar Ujala (in Hindi). Retrieved 6 December 2021.
  31. ^ "Agra witnesses first Metro train trial run". Hindustan Times. 11 July 2023. Retrieved 12 July 2023.
  32. ^ "PM Modi inaugurates priority section of Agra Metro; here's a look at the project". The Indian Express. 6 March 2024. Retrieved 6 March 2024.