Buzzard oil field

Summary

The Buzzard Oil Field is an oil field located in the North Sea Blocks 19/10, 19/5a, 20/6 and 20/1s.[1] It was discovered in 2001 by PanCanadian, and developed initially by PanCanadian's successor EnCana and then by Nexen. The oil field was initially operated and owned by Nexen which is now a subsidiary of China's CNOOC.

Buzzard Oil Field
An oil platform departing Hartlepool for the Buzzard field in 2010
CountryUnited Kingdom
RegionNorth Sea
Offshore/onshoreoffshore
OperatorCNOOC - 43%,
PartnersSuncor Energy - 30%, BG Group - 22%, Edinburgh Oil & Gas - 5%
Field history
Discovery2001
Start of production2007
Peak year2009
Production
Current production of oil85,500 barrels per day (~4.26×10^6 t/a)
Year of current production of oil2020
Estimated oil in place1,500 million barrels (~2.0×10^8 t)

The field edit

The total proven reserves of the Buzzard oil field are 240 million cubic metres (1.5 billion barrels), and production will be centered on 28,670 cubic metres (180,300 bbl) per day.[2]

The Buzzard reservoir has a low gas/oil ratio and requires pressure maintenance through water injection. Buzzard’s oil consists of medium sour crude: 32.6° API, 1.4% sulphur.[3]

Infrastructure edit

The Buzzard field development comprises four bridge-linked steel platforms: the wellhead facilities (W) for up to 27 production wells, production facilities (P), a platform supporting accommodation and utilities (UQ) and an oil stripper platform (PS).[3]

Processing edit

The oil processing facilities comprise a 3-phase (oil/vapour/water) Production Separator. Oil from the separator flows to the 3-phase Second Stage Separartor. Oil from the latter is 'spiked' with Natural Gas Liquids (NGL) from the gas dewpointing plant, then injected with a hydrogen sulphide (H2S) scavenger chemical prior to metering and export.[4]

Produced water from the Second Stage Separator is recycled to the Production Separator, and from there to the produced water treatment facilities using hydrocyclones before overboard disposal.[4]

Vapour from the two Separators is compressed in an Offgas Compressor and a LP/HP compressor. Compressed gas passes through a Mercury Removal Bed and an Acid Gas Removal system, which uses a counter-current flow of amine solvent, and then through a Mercaptans Removal Bed. The gas is dehydrated in a gas dehydration system which uses a counter-current flow of glycol. After dehydration the gas is cooled and passes through a Joule-Thomson valve to reduce its pressure and hence its temperature to remove liquids and achieve a gas hydrocarbon dewpoint. Natural Gas Liquids are separated and co-mingled with the export oil stream. Gas is compressed in the HP Compressors, some is used as gas lift on the production wells, some as fuel gas, and the remainder is exported.[4]   

Export edit

Oil is exported from Buzzard via an 18 inch pipeline from the Buzzard processing platform to the nearest point in the Forties to Cruden Bay System, approximately 28 km away. Oil flows to Cruden Bay and then onto the Kinneil Terminal. First oil was produced in December 2006.[3]

Gas is exported via a 250 millimetres (10 in) pipeline from Buzzard to the Captain ‘T’ point on the UK Frigg pipeline 29 km away. From there the gas is transported to the St Fergus Gas Terminal. Fuel gas can also be imported onto Buzzard from the Frigg pipeline.[2]

Production history edit

Buzzard was the largest discovery in UK waters for 20 years when it was found in 2001 and went on to become the largest-producing field in the region after starting up in 2007.

Once at a peak of more than 35,000 cubic metres (220,000 barrels) of oil equivalent per day in 2009, production has decreased to 13,590 cubic metres (85,500 barrels) of oil equivalent per day as of May 2020, according to Oil and Gas Authority (OGA) figures.[5]

Buzzard was temporarily shutdown twice in late 2019 for repairs to topside pipework.[6][7]

Expansion edit

Buzzard Phase 2 is a bid to go after additional reserves to the north of the main field with a subsea development tied-back to it, with expected peak production of 5,900 cubic metres (37,000 barrels) of oil equivalent per day.

The first stage includes installation of a subsea manifold, a new processing module for the platform and drilling of four production wells. First oil from Buzzard Phase 2 was expected in late 2020 but as of August 2020, CNOOC postponed the project to 2021. Chrysaor stated that the drilling results for Buzzard Phase 2 was "towards the lower end of expectations," with the project now expected to come on stream in December 2021.[8]

References edit

  1. ^ "Offshore Oil and Gas Activity". Oil and Gas Authority. Archived from the original on 2019-01-26. Retrieved 25 November 2019.
  2. ^ a b "Hebron". nalcorenergy.com. 2012. Retrieved 2013-05-29.
  3. ^ a b c "Offshore Technology - Buzzard Field". Offshore Technology. Archived from the original on 2004-11-03. Retrieved 24 November 2019.
  4. ^ a b c Process Sketch Oil and Gas export (2006)
  5. ^ "Updated: CNOOC postpones Buzzard Phase 2 project to extend life of North Sea mega-field - News for the Energy Sector". 25 August 2020.
  6. ^ "Buzzard Oil Field shutdown for repairs". Energy Voice. 4 October 2019. Archived from the original on 2020-08-05. Retrieved 25 November 2019.
  7. ^ "Buzzard oil field shutdown again as repairs compromised". Energy Voice. 21 October 2019. Archived from the original on 2019-10-22. Retrieved 25 November 2019.
  8. ^ "North Sea producer Chrysaor eyes 2021 output drop, muted Buzzard production | S&P Global Platts". 16 December 2020.