Cottbus-Drewitz Solarpark

Summary

The Cottbus-Drewitz Solarpark is a 30.2-megawatt (40,500 hp) photovoltaic power station, located on a former military airfield. It was completed in 11 weeks using Suntech STP 280 Wp panels.[1][2][3]

Cottbus-Drewitz Solarpark
Map
CountryGermany
LocationCottbus-Drewitz, Brandenburg
Coordinates51°56′N 14°32′E / 51.933°N 14.533°E / 51.933; 14.533
Construction beganAugust 2011
Commission dateOctober 2011
Construction cost58 million euros
Solar farm
TypeFlat-panel PV
Site area75.9 hectares (187.6 acres)
Power generation
Nameplate capacity30.2 MW
Annual net output27.68 GWh