MV Glen Sannox (2017)

Summary

MV Glen Sannox is a dual-fuel car and passenger ferry constructed at Ferguson Marine in Port Glasgow for Caledonian MacBrayne, planned to serve the Ardrossan to Brodick crossing. Initially expected to enter service in summer 2018, the ship only began its sea trials in February 2024.[5][6] It has been the subject of continuing political scandal known as the "ferry fiasco" regarding increased costs and lengthy delays.[7][8][9]

Passing Greenock when starting sea trials, 13 February 2024
History
NameGlen Sannox[1]
NamesakeMV Glen Sannox (1957) and Glen Sannox on the Isle of Arran
OperatorCaledonian MacBrayne
Port of registryGlasgow
RouteArdrossanBrodick
BuilderFerguson Marine, Port Glasgow, Inverclyde, Scotland
Cost£97 million original contract for two ferries; £340 million as of September 2022
Yard number801
Laid down17 February 2017
Launched21 November 2017
Christenedby Nicola Sturgeon
IdentificationIMO number: 9794513
StatusSea trials
General characteristics
Tonnage1,273 DWT[2]
Length102.4 m (335 ft 11 in)[2]
Beam17 m (55 ft 9 in)[2]
Draught3.4 m (11 ft 2 in)[2]
Installed power2 × Wärtsilä 34DF diesels[4]
Propulsion
Speed14.5 kn (26.85 km/h)[2]
Capacity
  • 1,000 passengers, 127 cars or 16 HGVs (planned)[1]
  • 852 passengers (actual)[3]
Shortly after launch, November 2017
Being towed back to Ferguson Marine after interim work at Garvel drydock, March 2023

Originally expected to enter service in 2018, [1] construction delays led to her launch being pushed back to November 2017, with the ship then expected to begin operation in late 2018 or early 2019.[10] After further delays, handover was expected between March and May 2023 - five years late.[11][12] On 16 March 2023, it was reported that further delays had pushed the vessel's entry into service to Autumn 2023;[13] in August 2023, a further delay to the start of the summer 2024 timetable was announced.[14] A further delay was announced on 19 April 2024 due to complications with the vessel's LNG powerplants, with the vessel now due to be delivered by 31 July 2024, however Ferguson Marine expect no further increase in cost. [15]

History edit

See also Ferry fiasco for the political controversies surrounding the construction of these units.

The State-owned enterprise CalMac, originally Caledonian MacBrayne Ltd, was formed in 1973 as a vessel owner and operator providing most of the ferry services to the Firth of Clyde and the Hebridean islands off the west coast of Scotland. In 2006, its roles were split to satisfy EU competition rules. As Caledonian Maritime Assets (CMAL) it continued to own the Caledonian MacBrayne fleet and order new ships, while CalMac Ferries Ltd (CalMac) was created as a separate company which successfully bid in open competitive tender for the contract to operate the services. Many of CalMac's ferries had been built by Ferguson Shipbuilders, which five years earlier had employed 300 people, but it had struggled to compete and CalMac orders were won by the Remontowa shipyard in Gdańsk, Poland.[16][17] In 2011 Fergusons successfully bid for two small ships for CMAL, funded by the Scottish Government's Low Emissions Hybrid Ferries project.[18][16]

Transport Scotland's Ferries Plan, published in December 2012,[19] included indicative proposals for two new vessels.[20] International emissions regulations tightened, and cleaner liquefied natural gas (LNG) fuel was adopted by ferry operators in Northern Europe,[21] particularly Norway. The Danish island of Samsø invited tenders for the first in the EU, and in June 2013 Remontowa was awarded the contract for this dual-fuel ferry, to be delivered in October 2014.[2][22] David MacBrayne Ltd bid to operate a ferry connecting Gotland in Sweden, with detailed proposals drawn up by CalMac, but in May 2014 this bid was reported unsuccessful.[23]

To prepare the Vessel Replacement and Deployment Plan (VRDP), Transport Scotland held tripartite monthly meetings with CMAL and CalMac, starting in October 2013. By agreement, CalMac led development of programmes for the major vessels.[24] In early July 2014 the Scottish Government, using CalMac's initial analytical work, authorised the procurement process. It aimed to name the preferred bidder by the end of March 2015, leaving only three weeks to produce tender documents. CMAL's head of vessels said at the time it was a "hugely challenging" timetable. CalMac quickly adapted work done for the Gotland ferry bid to produce the Specification of Technical and Operational Requirements, but made some errors.[16][20]

Glen Sannox is to be the first of two Scottish ferries capable of operating on either marine gas oil or LNG, with benefits of a marked reduction in carbon dioxide, sulphur and nitrous oxide emissions.[1] Her name was chosen from a shortlist by public ballot and recalls an earlier Arran ferry.[25]

The first steel was cut on 7 April 2016 and Glen Sannox was launched on 21 November 2017 by the then First Minister Nicola Sturgeon,[26][27] It has been reported that the vessel's bulbous bow was not fit for purpose at the time of the launch, and only fitted to be able to claim "milestone payments" from the Scottish Government.[28] The bridge windows were painted on,[27] and the funnels were not operational, but only for show for the launch.[28]

In August 2018, new Cabinet Secretary for Transport Michael Matheson said it had been confirmed that the ship was to be delivered in June 2019, followed by two months of crew familiarisation and sea trials.[29] Further dispute over the contract overrun led to the shipyard going into administration and being nationalised by the Scottish Government.[30][31]

A report produced after nationalisation indicated that Glen Sannox should be handed over to Caledonian Maritime Assets Ltd (CMAL) in the last quarter of 2021 and that completing the two ferries was likely to increase the total cost to over £207 million.[32] In April 2020, Ferguson Marine contracted with International Contract Engineering, a marine design consultant, to revise the design and outfitting of Glen Sannox in advance of her eventual delivery.[33]

 
MV Glen Sannox back at Ferguson Marine after drydock work in 2020

On 10 August 2020, tugs moved Glen Sannox to the Garvel dry dock in Greenock for remedial work including replacement of the bulbous bow, paintwork repair and removal of marine growth.[34] After additional work, the ship returned to the Fergusons shipyard in Port Glasgow on 9 September 2020.[35]

In October 2022, it was announced that Glen Sannox would initially operate only on marine gas oil, as vacuum sensors required for the LNG system were not available.[36]

Further delays to both ferries and increasing costs of £250 million, subsequently rising to £340 million by September 2022, have resulted in controversy surrounding the contract and the lack of transparency in the decision-making process.[37][38] The Scottish Government announced that key documents relating to the decision-making process had gone missing.[39]

 
MV Glen Sannox in Garvel drydock in March 2023

In September 2023, a failed safety audit meant that MV Glen Sannox was further delayed: among other issues, the Maritime and Coastguard Agency (MCA) insisted on the installation of additional staircases as a condition of approving a safety audit. The work meant that planned sea trials of the Glen Sannox were delayed until the first quarter of 2024, raising doubts over whether the ship will be available for the start of the 2024 summer season.[40] Meeting MCA safety regulations ultimately meant that the passenger capacity of both ferries had to be cut from a planned 1,000 to 852.[3] The ship began manufacturer's sea trials on 13 February 2024.[6]

Service edit

Glen Sannox is being built for the Ardrossan to Brodick crossing. She was originally intended to serve as a running mate to MV Caledonian Isles on the Ardrossan–Brodick and the Ardrossan–Campbeltown crossings.[7][8] In May 2023, it was announced that Glen Sannox's sister vessel, MV Glen Rosa, would also serve the Arran route.[41] However, the two new Arran ferries will initially be operating between Troon and Brodick for the first two or three years of their career, due to the planned upgrade works for Ardrossan harbour.[42]

References edit

  1. ^ a b c d "Caledonian Maritime Assets Limited- announces Scottish shipbuilder as preferred tenderer for two large ferries contract". CMAL. 31 August 2015. Retrieved 24 June 2017.
  2. ^ a b c d e f "Presentation to Arran ferry Committee" (PPT). CMAL. 10 April 2017. Retrieved 23 June 2017.
  3. ^ a b Williams, Martin (3 October 2023). "Scots fiasco ferries have to be cut in size for safety reasons". The Herald.
  4. ^ "Calmac picks Wärtsilä for two LNG ferries". Retrieved 23 June 2017.
  5. ^ "New CalMac ferry sets sail in first sea trial after six year delay". STV News. 13 February 2024. Retrieved 15 February 2024.
  6. ^ a b "Long-delayed Ferguson ferry Glen Sannox begins sea trials". BBC News. 13 February 2024. Retrieved 13 February 2024.
  7. ^ a b "Costs double on delayed CalMac ferry contract". BBC News. 18 December 2019. Retrieved 14 January 2020.
  8. ^ a b "Ferguson Marine update". Scottish Government. 18 December 2019. Retrieved 14 January 2020.
  9. ^ "Completion of CalMac ferries delayed six months". BBC News. 25 August 2020.
  10. ^ "Ferry MV Glen Sannox ready for launch at Port Glasgow yard". Greenock Telegraph. 19 November 2017. Retrieved 23 November 2017.
  11. ^ Dalton, Alastair (23 March 2022). "Ferguson Marine ferries for CalMac delayed by another eight months to 2023". The Scotsman.
  12. ^ Daisley, Stephen (24 March 2022). "The SNP's ferry mess". The Spectator.
  13. ^ "Delays to Calmac ferries at Ferguson Marine in Port Glasgow". Greenock Telegraph. 16 March 2023. Retrieved 17 March 2023.
  14. ^ "New CalMac ferries delay after safety changes ordered". BBC News. 23 August 2023. Retrieved 23 August 2023.
  15. ^ "Update to NZET Committee 19 April 2024". Ferguson Marine. Retrieved 20 April 2024.
  16. ^ a b c "Ten things we learned about Scotland's ferry fiasco". BBC News. 27 September 2022. Retrieved 7 April 2024.
  17. ^ "Shipbuilder clinches £17m contract". BBC News. 5 October 2000. Retrieved 16 March 2020.
  18. ^ "Low Emissions Hybrid Ferries project". SAFETY4SEA. 4 November 2011. Retrieved 8 April 2024.
  19. ^ "Scottish Ferry Services: Ferries Plan (2013-2022)". Transport Scotland. 26 March 2024. Retrieved 12 April 2024.
  20. ^ a b "Ferguson Marine: key documents". gov.scot. 18 December 2019. Retrieved 12 April 2024.
    20 August 2015 email from: Transport Scotland Ferries Unit, re Minister for Transport and Islands.
  21. ^ "Ferry deal set to create new jobs". CMAL Caledonian Maritime Assets Ltd. 31 August 2015. Retrieved 16 April 2024.
  22. ^ "Denmark soon to get its very first LNG-fuelled domestic ferry". Skipsrevyen forsiden (in Norwegian Bokmål). 27 June 2013. Retrieved 12 April 2024.
  23. ^ Ross, David (3 May 2014). "CalMac bid to run European ferries". The Herald. Retrieved 12 April 2024.
  24. ^ "Vessel Replacement and Deployment Plan 2014 report (VRDP)". Transport Scotland. 2 October 2015. Retrieved 14 April 2024.
  25. ^ "CMAL announces name of first LNG ferry". CMAL. 1 June 2017. Retrieved 24 June 2017.
  26. ^ "In Pictures -- Launch Of Ferry Glen Sannox At Port Glasgow". Inverclyde Now. 21 November 2017. Retrieved 26 August 2020.
  27. ^ a b Swindon, Peter (8 September 2019). "First Minister launched new Arran ferry at Ferguson shipyard with painted-on 'windows'". Sunday Post. Retrieved 12 March 2021.
  28. ^ a b Grossman, David (6 August 2021). "Scotland's Ferry Fiasco: What went wrong?". BBC Newsnight. Retrieved 7 August 2021.
  29. ^ Fisher, Paul (15 August 2018). "New Arran Ferry set to launch next June - government confirms". Ardrossan Herald. Retrieved 15 August 2018.
  30. ^ Fraser, Douglas (18 August 2019). "Shipyard forecast: Sunshine becoming misty". BBC News. Retrieved 20 August 2019.
  31. ^ Fraser, Douglas (24 June 2021). "Delivery date for overdue ferries slips again". BBC News. Retrieved 7 August 2021.
  32. ^ Ferguson Marine: report on cost and programme for vessels 801 and 802, Scottish Government, 9 December 2019, retrieved 23 December 2019
  33. ^ "Charting a New Course for Scottish Ferry Project". The Motorship. 6 April 2020. Retrieved 11 April 2020.
  34. ^ "Clyde Shipping - Dry Dock Work For MV Glen Sannox Is 'Major Step' Forward". Inverclyde Now. 10 August 2020. Retrieved 11 August 2020.
  35. ^ "Ferry Returns To Shipyard After Dry Dock Work". Inverclyde Now. 9 September 2020. Retrieved 9 September 2020.
  36. ^ "New fault means environmentally friendly Scots fiasco ferry cannot initially run green". The Herald. 29 October 2022. Retrieved 30 October 2022.
  37. ^ "Nicola Sturgeon: Buck stops with me over ferry contract row". BBC News. 24 March 2022. Retrieved 25 April 2022.
  38. ^ "Cost to taxpayer of Scotland's ferry fiasco soars to nearly £340m". HeraldScotland.
  39. ^ Bol, David (22 April 2022). "Sturgeon denies 'cover-up' over missing key ferries contract document". HeraldScotland. Retrieved 25 April 2022.
  40. ^ "Concern over whether Scots ferry fiasco vessel will set sail after safety audit fail". The Herald. 12 September 2023.
  41. ^ "Competition Launched to Name Dual Fuel Ferry". Caledonian Maritime Assets Ltd (CMAL). 2 August 2023. Retrieved 2 August 2023.
  42. ^ "Ardrossan Harbour redevelopment". North Ayrshire Council. Retrieved 1 September 2023.