Summary

MV Loch Seaforth is a ferry operated by Caledonian MacBrayne between Stornoway and Ullapool. She was launched on 21 March 2014 and entered service in mid-February 2015, replacing both the former vessel, 1995-built MV Isle of Lewis and a chartered freight vessel (latterly MS Clipper Ranger).

Arriving in Stornoway, May 2021.
History
United Kingdom
Name
NamesakeLoch Seaforth
OwnerCaledonian Maritime Assets
OperatorCaledonian MacBrayne
Port of registryGlasgow
RouteStornowayUllapool
Ordered22 June 2012
BuilderFlensburger Schiffbau-Gesellschaft MBH and Co KG, Flensburg, Germany
Cost£42 million
Yard number764
Launched21 March 2014
Christenedby Joan Murray
In service16 February 2015
Identification
General characteristics
TypePassenger/Ro-Ro Cargo Ferry
Tonnage
Displacement3496
Length117.90 m (386 ft 10 in) (Overall) 111.14 m (364 ft 8 in) (Between Perpendiculars)
Beam19.2 m (63 ft 0 in)
Draught4.8 m (15 ft 9 in)
Depth7.0 m (23 ft 0 in)
Installed power
  • 2 × 4000 kW Wärtsilä 8 L 32 (main)
  • 3 × 1600 kW (generators)
  • 2 × 700 kW (auxiliary & emergency generators)
  • 3 × 900 kW thrusters
Propulsion
  • Twin 4.10 m diameter controllable pitch propellers
  • 2 Bow Thrusters
  • 1 Stern Thruster
Speed19.2 kn (35.6 km/h)
Capacity
  • 700 passengers
  • 143 cars (on main deck and 2 mezzanine decks), or
  • 20 commercial vehicles
  • 376 lane metres
Crew43
Notes[2]

History edit

Scottish Transport Minister Keith Brown MSP announced on 8 June 2012 there was to be a replacement vessel for the Stornoway-Ullapool route.[3] Two weeks later on 22 June, Caledonian Maritime Assets announced that the contract to construct had been signed with Flensburger Schiffbau-Gesellschaft MBH and Co KG in Germany. Construction commenced on 16 September 2013 with the cutting of the first steel. The shed at the Flensburger shipyard suffered damage in the St. Jude storm, delaying delivery by about two weeks.

The building of the ferry was financed by the Lloyds Banking Group who then leased Loch Seaforth to Caledonian Maritime Assets Ltd (CMAL) who in turn chartered her to the operator, Caledonian MacBrayne.[4] Ownership remained with Lloyds until 10 October 2019, when CMAL purchased Loch Seaforth outright, ending the lease after almost five years.[5] Over a month after buying Loch Seaforth outright from Lloyds, CMAL announced that they paid £36 million for her.[6]

The name was chosen in a competition run by CMAL, reviving that of MacBrayne's 1947 Stornoway mailboat.[7] Before launch, there was speculation over the timetables for the new vessel. Despite being capable of 24-hour operation, there were concerns that she would not carry out 24-hour sailings in summer.[8]

Loch Seaforth was launched on 21 March 2014 and christened by Joan Murray, the eldest daughter of the late Captain John Smith, master of the original 1947 mailboat.[9] She departed Germany on her delivery voyage on 4 November 2014 and arrived in Greenock three days later. After sea trials, she was laid up as the piers at Stornoway and Ullapool were unfinished.

Loch Seaforth sailed to Ullapool on 12 November 2014, to conduct berthing trials, which were successful and returned to the Clyde.[10] On 6 December 2014, she sailed to carry out crew familiarisation tests at Stornoway, despite the terminal not being ready to accommodate her. Once again, she returned to the Clyde.[11]

Loch Seaforth undertook berthing trials at the new pier at Stornoway on 4 February 2015. Her first commercial sailing was the overnight freight sailing on 10/11 February. An open day for public viewing was held in Stornoway on 13 February, and she gave her first passenger crossing of the Minch the following day. She entered public service on 16 February, initially on a 'phasing-in' basis, but full-time, effectively relieving Isle of Lewis, which was delayed in leaving drydock in Birkenhead during her annual overhaul. On 5 March, Loch Seaforth developed a ventilation fan problem at Ullapool, leaving the Isle of Lewis to take passengers and their vehicles to Stornoway, putting her new backup status to the test.[12]

The Ullapool port reopened in May 2015 with a new linkspan. Loch Seaforth was finally able to take up her full round-the-clock schedule between Stornoway and Ullapool. Chartered freight vessel, MS Clipper Ranger left Stornoway for Heysham after staying in reserve for any teething troubles. MV Isle of Lewis remained as a backup vessel on the route until the summer of 2015,[8][13] undertaking extra sailings on Fridays and Saturdays during the summer of 2015 to cope with demand.

Loch Seaforth was withdrawn from service due to engine failure on 16 April 2021.[14] The ship went for repairs and returned to service on 31 May 2021.[15] MV Isle of Lewis returned to maintain the service, at reduced capacity, with MV Isle of Arran[16] and then MV Hebridean Isles[17] providing a night freight service. This redeployment caused disruption on several crossings across the CalMac network.[16] From 19 July 2021, MS Arrow was chartered by Caledonian MacBrayne to carry freight on the Stornoway to Ullapool route, freeing MV Loch Seaforth to make additional passenger crossings.[18]

Layout edit

MV Loch Seaforth is of ro-ro design with bow and stern ramps. She has "clam shell" bow doors that open sideways. The car deck provides 376 lane-metres[19] and is partially open at the stern. Car capacity is augmented by two hoistable mezzanine decks.[7] Five stairways and two passenger lifts give access to the main passenger accommodation on Deck 5.[20] This includes a Quiet Lounge, a shop, a Coffee Cabin, a play area and a gaming area. Towards the bow is a cafeteria, with an observation lounge looking forwards, on the deck above.[20] There is outside seating towards the stern on decks 6 and 7.[20]

The combination of diesel electrical and diesel mechanical propulsion give a high level of redundancy.[21] The two Wärtsilä 8L 32 main engines can use IFO 40 and MDO fuel oils.[19] Three backup diesel generators would allow her to operate to timetable even with one main engine out of service.[7]

Service edit

MV Loch Seaforth is operated by Caledonian MacBrayne on the Stornoway to Ullapool route. She provides passenger sailings through the day and an overnight freight service.

From 29 October to 12 November 2015, Loch Seaforth was relieved by MV Isle of Lewis and the NorthLink vessel MS Hildasay.[22]

From the summer 2023 timetable she has been slowed down from 2 hours 30 minutes to 2 hours 40 minutes on the Stornoway to Ullapool route, the same journey time as Isle of Lewis until 2004 when her journey time was increased by five minutes. This is due to a combination of fuel costs and growth on the hull slowing her down. In March 2023, Robert Morrison, CalMac Director of Operations, stated that the timetable set upon Loch Seaforth's entry to service was "ambitious" and "hard to deliver on a good day".[23]

On 10 April 2023, Loch Seaforth suffered engine control issues en route from Stornoway to Ullapool. Upon arrival in Ullapool, services were suspended, with some travellers having to re-route via the Uig - Tarbert service.[24]

References edit

  1. ^ a b "Loch Seaforth". Caledonian MacBrayne. Caledonian MacBrayne. Retrieved 5 December 2019.
  2. ^ "MV Loch Seaforth". CMAL. Retrieved 25 June 2018.
  3. ^ "'Greener and faster' ferry ordered for Stornoway-Ullapool route". BBC News. 8 June 2012. Retrieved 14 April 2013.
  4. ^ "Financing Vital Ferry Service". Lloyds Banking Group. Retrieved 24 June 2018.
  5. ^ "CMAL acquires Ullapool to Stornoway's MV Loch Seaforth". BBC News. 10 October 2019. Retrieved 10 October 2019.
  6. ^ Comms, Clark (26 November 2019). "CMAL PUBLISHES PURCHASE PRICE OF MV LOCH SEAFORTH". CMAL Caledonian Maritime Assets Ltd. Retrieved 13 May 2023.
  7. ^ a b c "Loch Seaforth". Ships of Calmac. Retrieved 18 January 2021.
  8. ^ a b "Concerns about timetables as new ferry delayed by storm". Stornoway Gazette. 26 January 2014. Retrieved 5 February 2014.
  9. ^ "Loch Seaforth Expected to be launched on March 21st". Stornoway Gazette. 24 February 2014. Retrieved 15 March 2014.
  10. ^ "New ferry for Stornoway-Ullapool route starts sea trials". BBC News. 13 November 2014. Retrieved 13 November 2014.
  11. ^ "MV Loch Seaforth in Stornoway visit". Hebrides News. 5 December 2014. Retrieved 13 December 2014.
  12. ^ "New £43 million ferry breaks down". Hebrides News. 6 March 2015. Retrieved 6 March 2015.
  13. ^ "MV Loch Seaforth to start service on September 8th". Stornoway Gazette. 11 March 2014. Retrieved 15 March 2014.
  14. ^ "CalMac's largest ferry out of action until May". BBC News. 23 April 2021. Retrieved 24 April 2021.
  15. ^ "New problems uncovered on CalMac's Loch Seaforth". BBC News. 14 May 2021. Retrieved 17 May 2021.
  16. ^ a b "Row over freight services after ferry breakdown". BBC News. 22 April 2021. Retrieved 17 May 2021.
  17. ^ "Stornoway relief freight ferry being despatched to calmer waters". Hebrides News. 5 May 2021. Retrieved 18 May 2021.
  18. ^ "MV Arrow - Ullapool to Stornoway". CalMac. Retrieved 21 July 2021.
  19. ^ a b "Loch Seaforth updates FSG ro-pax design". The Motorship. 31 October 2014. Retrieved 25 June 2018.
  20. ^ a b c "Welcome on board MV Loch Seaforth" (PDF). CalMac. Retrieved 24 June 2018.
  21. ^ "RoPax Ferry Loch Seaforth". Flensburger Schiffbau-Gesellschaft. Retrieved 25 June 2018.
  22. ^ "CALMAC FINALISES DRY DOCK REFIT PROGRAMME". Am Paipear. 28 October 2015. Retrieved 29 October 2015.
  23. ^ "Video of Robert Morrison's presentation". Clyde River Steamer Club. Retrieved 26 February 2024.
  24. ^ "CalMac's biggest ferry MV Loch Seaforth hit by technical fault". BBC News. 11 April 2023. Retrieved 11 April 2023.