Virginia Avenue Tunnel

Summary

The Virginia Avenue Tunnel is a railroad tunnel in Washington, D.C. owned by CSX Transportation. It is part of the CSX RF&P Subdivision and serves freight trains along the eastern seaboard routes, providing a bypass around Union Station.

Virginia Avenue Tunnel
Undated photograph of the northwest entrance to the tunnel taken from New Jersey Avenue SE
Overview
LocationWashington, D.C.
SystemCSX Transportation
Operation
Opened1872
Rebuilt2015–2018
OwnerCSX Transportation
OperatorCSX Transportation
TrafficTrain
CharacterFreight
Technical
Length3,788 feet (1,155 m)
No. of tracks2
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Operating speed25 mph (40 km/h)
Tunnel clearance18.25 feet (5.56 m) max. for original tunnel; 21.25 feet (6.48 m) for rebuilt tunnels[1]: 2–4 [2]: 44 
Width28 feet (8.5 m)

The double-tracked tunnel is located under Virginia Avenue SE, from 11th Street SE to 2nd Street SE. The eastern portal connects to the Anacostia Railroad Bridge and the CSX Capital Subdivision. At the western end the RF&P Sub runs to the Long Bridge into Virginia.[3]

CSX rebuilt the tunnel to replace its deteriorated structure and increase capacity to allow double-stacked containers to pass through. Construction began in 2015 and the project completed in 2018.[4]

History edit

The tunnel was constructed in 1872 by the Baltimore and Potomac Railroad (B&P), later controlled by the Pennsylvania Railroad. It originally served the B&P station on the present-day site of the National Gallery of Art, on the National Mall at 6th & B Street NW (today's Constitution Avenue). The tunnel was built using the cut and cover method. It was constructed of ashlar stone for the sidewalls, and brick and stone for the arches. In 1904 the tunnel was extended to its present length due to a track relocation.[3]

Initially the tunnel served both freight and passenger service until Union Station's opening in 1908, and since that time it has been freight-only.[5] The tunnel's second track was removed in 1936 to accommodate electrification and increasingly large railroad equipment.[6]

Tunnel modifications edit

In 2008, CSX proposed to modify or replace the tunnel to provide room for a second track and sufficient height to allow use of double-stack freight cars and autoracks. The railroad also planned to address the tunnel's deteriorated structure, in particular its cracked masonry and failing drainage system.[7]

CSX sought government funding in a public-private partnership as part of its National Gateway initiative.[8][9] In 2011, CSX announced that it would fund the tunnel project itself.[10] In 2012, CSX and government agencies considered four design alternatives for a new tunnel, conducting public outreach meetings, and preparing an environmental impact assessment for each of the alternatives. A final decision on the selected alternative was expected in spring 2013.[11]

Environmental impact statements and objections to the proposal edit

CSX released its Draft Environmental Impact Statement (DEIS) in July 2013.[12] During the comment period, many Capitol Hill and Navy Yard residents raised objections to the DEIS. Organizations which submitted comments to CSX criticizing elements of the DEIS include Casey Trees, the Capitol Hill Restoration Society (CHRS),[13] the Sierra Club, and the Committee of 100 on the Federal City. CHRS filed an additional comment concerning review of the Virginia Avenue Tunnel project under Section 106 of the National Historic Preservation Act of 1966, raising concerns about negative project impacts on historic structures (including those of religious and military value), economic impact on Barracks Row Main Street, and the project's "adverse effect on the L'Enfant Plan."[14] Individuals in favor of the tunnel have dismissed the claims as being a classic case of NIMBYism.[citation needed] The United States Environmental Protection Agency also released an official opinion on the DEIS in which they identified in detail "deficiencies and areas of concern, including environmental justice, children's environmental health, cumulative impacts, and community impacts, especially vibration, parks, visual, and utility disruptions."[15] CSX stated in the DEIS that it wishes to keep rail traffic moving during the construction by using the cut and cover method, which would avoid over-stressing their infrastructure while lowering the cost of the project. This would require the on-and-off closure of varying parts of Virginia Avenue for three years, however.

After the 2013 Lac-Mégantic disaster and the ensuing national controversy about crude oil being transported by rail,[16] the improvement of the tunnel leading to increased crude shipments through the city became a major concern. When asked about this during a public hearing, CSX said that the improvement of the tunnel would not lead to increased shipments of crude oil.[17]

The D.C. Department of Transportation (DDOT) and Federal Highway Administration (FHWA) announced in 2013 that the Final Environmental Impact Statement (FEIS) would be released for public review in the following few weeks. After release, the statement will be up for a 30-day public review period, during which a public meeting will also be held. The FHWA will then decide if it will approve the project; if approved, the DDOT then would decide if it will grant construction permits to CSX. Public funds would not be allocated to the project, as CSX has said they will fund the estimated US$200 million project in full.

Some opponents of the project like James McPhillips, an attorney, activist, and resident of the Navy Yard neighborhood, suggest that the fact the report has made it into the final stage means that CSX, DDOT, and the FHWA have cut corners and collaborated to get the project approved as soon as possible without addressing the concerns of locals. In doing so, the opposition says that the prospect other potentially feasible options that residents would approve of were unfairly ignored, and should have been researched before the impact of the current proposal. The DEIS published by CSX outlines three potential options for tunnel renovation. Congressional Delegate Eleanor Holmes Norton asked the U.S. Secretary of Transportation Anthony Foxx in April 2014 on behalf of the community to expedite the release of the FEIS to provide closure on the issue, which had been going on 6 years at that point. "I ask that you help ensure the prompt release of the Final (Environmental Impact Statement) for the Virginia Avenue Tunnel project so that the surrounding community is aware of the preferred alternative, any impacts this project may have on them, and any mitigation and benefits to the surrounding community."[18][19]

FHWA released a 2,639 page FEIS on June 13, 2014.[12] The final recommendation rejected options that called for re-routing train traffic off of Capitol Hill in favor of new rail lines through Southern Maryland, which would have cost between $3.2 and $4.2 billion. Instead, the selected alternative would run trains through the Virginia Avenue Tunnel while a portion of the new project is constructed. Next, trains would use the new tunnel while a second one is completed.[20]

The FEIS included offers of some financial compensation to "residents most harmed by the project" although residents claim the money is not worth the risk the project poses to their lives and livelihoods.[21][22]

The Washington Post discovered in Appendix A of the FEIS that DDOT issued an occupancy permit in 2012 guaranteeing CSX Transportation the right-of-way at Virginia Avenue SE and adjacent roads prior to the completion of the review period. Additional agreements indicate that upon conclusion of the project, CSX would be entitled to a permanent right-of-way.[23][24]

Delegate Norton asked the DOT Secretary for a review period extension on the Virginia Avenue Tunnel EIS, saying "Residents will be substantially affected, often negatively, by any construction on the Virginia Avenue Tunnel, and they need to be afforded sufficient time to review the documents and the ability to alert federal officials to any oversights.”[25][26]

FHWA approval edit

The FHWA issued a Record of Decision, approving the tunnel project on November 4, 2014.[12] Lawsuits attempting to stop the project were denied in court decisions, and construction on the project began in 2015.[27]

Project completion edit

The first phase of the project was completed on December 23, 2016, when the first double-stack train passed through the newly constructed parallel tunnel.[28] The full project was completed in fall 2018.[4]

See also edit

References edit

  1. ^ "Final Environmental Impact Statement - Chapter 2" (PDF). Virginia Avenue Tunnel. CSX Transportation. Retrieved 9 January 2017.
  2. ^ Schmidt, Brian (February 2017). "National Gateway Realized". Trains. 77 (2): 38–45.
  3. ^ a b U.S. Federal Railroad Administration, Washington, DC and Maryland Department of Transportation, Baltimore, MD (2011). "Baltimore's Railroad Network: Analysis and Recommendations." January 2011. pp. 11-1, 11-2.
  4. ^ a b "Virginia Avenue Tunnel: Project Overview". Projects and Partnerships. CSX. Retrieved 2021-09-28.
  5. ^ National Railway Historical Society, Washington, D.C. Chapter. "Washington Railroad History Timeline" at #14.
  6. ^ "About the Tunnel."
  7. ^ "FAQs". Virginia Avenue Tunnel. CSX Transportation. Retrieved 2015-07-26.
  8. ^ CSX Corporation, Jacksonville, FL (2008). "CSX Announces National Gateway to Improve Flow of Freight." 2008-05-01.
  9. ^ Metropolitan Washington Council of Governments, Washington, DC (2009). "CSX National Gateway Projects in the Washington Region." Accessed 2009-12-05.
  10. ^ CSX (2011-05-18). "CSX Commits Additional $160 Million to National Gateway." Press release.
  11. ^ "Virginia Avenue Tunnel Project: Environmental Impact Statement & Section 106 Coordination; Public Meeting" (PDF). Virginia Avenue Tunnel. CSX Transportation. 2012-09-27. Presentation materials.
  12. ^ a b c "NEPA Process Archive". Virginia Avenue Tunnel. CSX Transportation. Retrieved 2015-12-25.
  13. ^ "Capitol Hill Restoration Society  » CSX Tunnel". Capitol Hill Restoration Society. Retrieved 13 September 2014.
  14. ^ "Capitol Hill Restoration Society" (PDF). Chrs.org. Retrieved 7 October 2014.
  15. ^ Rudnick, Barbara (2013-09-24). "Re: Draft Environmental Impact Statement and Section 4(f) Evaluation, Virginia Avenue Tunnel Reconstruction, Washington, D.C., July 2013, CEQ# 20130207" (PDF). Philadelphia, PA: U.S. Environmental Protection Agency. Memorandum to DDOT and FHWA.
  16. ^ Wolfe, Kathryn A.; King, Bob (2014-06-18). "Oil boom downside: Exploding trains". Politico.
  17. ^ "Navy Yard Residents to Council: We Really, Really Do Not Want the CSX Tunnel - City Desk". Washington City Paper. Retrieved 13 September 2014.
  18. ^ Lazo, Luz (2014-04-02). "Norton urges decision on CSX tunnel project in SE". Washington Post.
  19. ^ Lazo, Luz (2014-06-06). "A key step for Virginia Avenue Tunnel project expected soon". Washington Post.
  20. ^ "Study: hazardous rail cargo near Capitol should continue". WUSA9.com. 2014-06-13. Retrieved 7 October 2014.
  21. ^ "Company Offers Cash To Ease D.C. Residents' Fear Of Possible Oil Trains Through Neighborhood - ThinkProgress". Thinkprogress.org. Retrieved 7 October 2014.
  22. ^ "Disastrous record shows tank car hazard". MSNBC. Retrieved 7 October 2014.
  23. ^ Lazo, Luz (2014-06-19). "DDOT's early commitment to CSX tunnel project in Southeast D.C. irks residents". Washington Post.
  24. ^ "DC Pre-Approves CSX Tunnel Plans Before Federal Environmental Study". DC Safe Rail. Retrieved 7 October 2014.
  25. ^ "Norton Asks DOT Secretary for Review Period Extension on Virginia Avenue Tunnel EIS". Congresswoman Eleanor Holmes Norton. 2014-06-24. Press release.
  26. ^ Lazo, Luz (2014-06-25). "D.C. residents need more time to review CSX tunnel project, Norton says". Washington Post.
  27. ^ Lazo, Luz (2015-05-28). "Opponents of Virginia Avenue Tunnel project lose again". The Washington Post.
  28. ^ "First New Virginia Avenue Tunnel Complete". Virginia Avenue Tunnel. CSX Transportation. 2016-12-23. Retrieved 2017-01-08.
  • Wright, William (2006). "Chapter 1: Railroading Washington." History of Union Station. Unpublished manuscript. www.washingtonunionstation.com.

External links edit

  • Heavy Rail Track and Structures in Washington DC - BelowTheCapital.org
  • Virginia Avenue Tunnel Project - New tunnel project status; maps, photos & drawings

38°52′39″N 76°59′28″W / 38.877399°N 76.9911°W / 38.877399; -76.9911